Control Point Name Commissioning & Start-up Plan
Owner Production Operations
Definition/Context (“What”)

The CSU Plan describes the methodology and resources to be used for carrying out all Completions, Commissioning and Start-up activities for the project as well as for developing the CSU schedules, logic, and Work Execution Flow Shemes (WEFS). It addresses the identified risks that can prevent the project from delivering a successful commissioning and start-up and captures the mitigating actions.

As a minimum the CSU plan shall cover the following Project Standard Controls:

Purpose/Intent (“Why”) The CSU plan ensures that all parties are aligned on the roles and responsibilities for commissioning and start-up of the Asset and it defines the resources and methodologies used.
Standards Project Standards
Phase(s) Execute
Accountable for delivery Project Manager
Guidance CSU Plan Template