Title Description

Context

Poor alignment of construction and Commissioning and Start-up (CSU) priorities can lead to inefficient execution and/or HSSE & SP incidents during CSU.

Activity

Develop detailed integrated construction and CSU plan to address:

  • construction work pack completion from area to system focus to align with commissioning requirements and priorities
  • simultaneous operations (SIMOPS) assessment of both construction and commissioning activities on the same scope of work

Purpose

To ensure detailed alignment of construction and CSU activities and, thereby,  a safe and efficient delivery - optimised critical path - of the project.

To minimise any unnecessary simultaneous operations that could impact execution efficiency and/or HSSE & SP incident risk.

Requirements from other Standards

None

Evidence recorded in

Commissioning and Start-up Plan

Accountability for meeting Control Intent 

Project Manager

Phase

Execute