Control: 4.E.14 Engineering Ready for Construction
Title | Description |
Context |
At the start of construction inefficient and/or poor quality construction delivery can be caused by the following engineering conditions:
|
Activity |
Conduct Approved For Construction (AFC) design readiness reviews. |
Purpose |
To ensure sequencing, integrity and quality of engineering and procurement deliverables i.e. to confirm delivery in line with workface planning and optimal path of construction- thereby safeguarding construction efficiency, integrity, quality and safe execution of contracted scope. |
Requirements from other Standards |
None |
Evidence recorded in |
Approved for Construction Report |
Accountability for meeting Control Intent |
Project Manager |
Phase |
Execute |