Title  Description

Context

On site work which starts too early relative to project management and HSSE & SP site preparedness, can result in poor execution performance and/or HSSE & SP incidents during the early works activities of the project.

Activity

Conduct a structured contractor and owner review to establish readiness for early works, taking into account engineering, procurement and resourcing status, the appropriate HSSE & SP approvals, guidelines and training.

Purpose

To ensure robust execution performance at the start of early works. All appropriate deliverables are completed and contractor’s organisation and resources are fit for duty and ready for Execute. To make sure safety performance starts strong, continue strong and finishes strong through final scope completion.

Requirements from other Standards

None

Evidence recorded in

Early Works Readiness Report

Accountability for meeting Control Intent

Project Manager

Phase

Define