Title
Description

Context

Experience from recent projects shows that, if incorrect decisions are made on constructability strategy, tactics and recognition of latent construction risk, they do not achieve world class HSSE & SP performance. These are caused by a lack of construction expertise during constructability reviews and planning.

Activity

With input by the relevant disciplines during constructability reviews ensure all execution HSSE & SP risks are understood and integrated in the project delivery. Engineer the risk out in the final design.

Purpose

Ensure identification of significant execution (construction, installation and commissioning) HSSE & SP risks during the design stage and development of engineering solutions, using a hierarchy of controls, to mitigate them to ALARP.

Requirements from other Standards

Evidence recorded in

Basic Design and Engineering Package

Accountability for meeting Control Intent 

Project Manager

Phase

Define